@startgantt Diagramme de Gantt projet Pronto
projectscale weekly zoom 2.2
Language fr
hide footbox
Project starts 2025-02-04
......@@ -11,7 +12,7 @@ Project starts 2025-02-04
$today is colored in grey
[Capteur V1] as [C1] starts 2025-02-13 and requires 30 days and is 80% completed
[Capteur V1] as [C1] starts 2025-02-13 and requires 30 days and is 100% completed
[Capteur autonome] as [C2] starts 2025-02-20 and ends at [C1]'s end
......@@ -20,14 +21,14 @@ $today is colored in grey
[Capteur autonome suite] as [C2s] starts at [C2]'s end and requires 17 days
[C2s] displays on same row as [C2] and is 90% completed
[GW V2] starts 2025-02-20 and requires 40 days and is 90% completed
[GW custom] starts 2025-02-20 and requires 40 days and is 40% completed
[GW V2] starts 2025-02-20 and requires 40 days and is 100% completed
[GW custom] starts 2025-02-20 and requires 40 days and is 100% completed
[Integration] as [I] starts 2025-03-22 and ends 2025-04-12 and is 5% completed
[Integration] as [I] starts 2025-03-22 and ends 2025-04-12 and is 85% completed
[Revue de projet] happens 2025-03-27
[Qualifier le système] starts at [I]'s end and requires 2 weeks and is 0% completed
[Qualifier le système] as [Q] starts at [I]'s end and requires 2 weeks and is 25% completed
[Recette du projet] happens 2025-05-23
......@@ -35,13 +36,20 @@ $today is colored in grey
[Capteur autonome (deadline dépassée)] as [C2sb] starts at [C2s]'s end and ends $today
[C2sb] displays on same row as [C2s] and is colored in IndianRed/DarkRed
[GW V2 (deadline dépassée)] as [GW2b] starts at [GW V2]'s end and ends $today
[GW V2 (deadline dépassée)] as [GW2b] starts at [GW V2]'s end and ends 2025-05-06
[GW2b] displays on same row as [GW V2] and is colored in IndianRed/DarkRed
[GW custom (deadline dépassée)] as [GWCb] starts at [GW custom]'s end and ends $today
[GW custom (deadline dépassée)] as [GWCb] starts at [GW custom]'s end and ends 2025-05-06
[GWCb] displays on same row as [GW custom] and is colored in IndianRed/DarkRed
[Capteur V1 (deadline dépassée)] as [C1b] starts at [C1]'s end and ends $today
[Capteur V1 (deadline dépassée)] as [C1b] starts at [C1]'s end and ends 2025-05-20
[C1b] displays on same row as [C1] and is colored in IndianRed/DarkRed
[Intégration (deadline dépassée)] as [Ib] starts at [I]'s end and ends $today
[Ib] displays on same row as [I] and is colored in IndianRed/DarkRed
[Qualifier le système (deadline dépassée)] as [Qb] starts at [Q]'s end and ends $today
[Qb] displays on same row as [Q] and is colored in IndianRed/DarkRed
@endgantt
\ No newline at end of file
@startgantt Diagramme de Gantt projet Pronto
projectscale weekly zoom 2.2
Language fr
hide footbox
Project starts 2025-02-04
today is 2025-03-25
today is colored in grey
[Capteur V1] as [C1] starts 2025-02-13 and requires 30 days
[Capteur autonome] as [C2] starts 2025-02-20 and ends at [C1]'s end
[Document de cadrage] happens 2025-02-23
[Capteur autonome suite] as [C2s] starts at [C2]'s end and requires 17 days
[C2s] displays on same row as [C2]
[GW V2] starts 2025-02-20 and requires 40 days
[GW custom] starts 2025-02-20 and requires 40 days
[Integration] as [I] starts 2025-03-22 and ends 2025-04-12
[Revue de projet] happens 2025-03-27
[Qualifier le système] as [Q] starts at [I]'s end and requires 2 weeks
[Recette du projet] happens 2025-05-23
@endgantt